To provide you with the best possible service, we make use of cookies. By accepting tracking cookies, you will be recognized. In that way, we can customize our website to your personal preferences and we can show you relevant information and advertisements on our website and others. If you agree, please click ‘I agree’. You can always view your settings and have them changed. For more information, see our cookie and privacy policy.

I agree

Explanation installation template for grouting and welding ETL OH5.

Explanation installation template for grouting and welding ETL OH5.

A major advantage of the ETL OH5 pump type is the possibility that the pump installation work can be started at an early stage. By pouring of the sole plate and the welding of the pipework at the location before the actual pump is on-site the overall lead time can be significantly reduced.

For this Rodelta has developed the extra “Grouting and welding ETL installation template” which is mounted on the final sole plate of the pump to be supplied.
(The template is a extra ETL option *)

*This template and sole plate “with all grouting parts for pouring” will be delivered with a shorter lead time.

 

Explanation of the installation template

A pedestal for the ETL (OH5) pump will be poured in accordance with dimensions as specified in the DEP.

The original sole plate of the new pump will be assembled with the foundation anchors and leveling bolts and placed on top of the pedastal. Ensure that the anchors protrude sufficiently high (Sole plate and foundation plate ETL) After this the sole plate will be adjusted to height and level by turning the bolts. Than the wooden formwork shall be applied (shape acc DEP)

The next step can take place, the sole plate can be poured in with shrink-free mortar.

After hardening of the concrete and tightening of the foundation anchors the wooden formwork can be removed.

The installation template for grouting and welding will be assembled by using the foundation anchors on top of the sole plate.

Before to start welding of the pump pipework make sure that the gaskets are applied!

When the welding is done, the template can be removed between the pipes. It is wise to do this when the definitive ETL (OH5) pump unit will be installed. This ensures that no unnecessary contamination can get into the pipes. Of course it is advisable to check if the pipes are free of contamination before the definitive pump will be installed.

Place the final ETL between the pipework. Install the gaskets and fix the bolts.

This working method contributes to a considerable lead-time reduction of the installation process. This because processes on-site can run in parallel with the production of the new ETL OH5 pump. Bringing forward these grouting and welding activities leads to more flexibility with regard to the start and continuation of these activities on-site. Delays or postponement work can be compensated by the space created in this way in the planning.

Explanation installation template for grouting  and welding ETL OH5.
OH2 API pump

ETL option on OH2

This working method is not possible / desirable with an OH2 type pump because the foundation plate which must be poured into concrete is a crucial part in the alignment of pump, coupling and motor. This is in contrast to the OH5 pump design.

To ETL OH5 (API 610)
Our range

Partner in pump projects

From selecting a model to choosing the perfect setup: we’ll help you find a Rodelta solution that’s right for you.

Others also looked at: To our range

Uw browser is niet meer van deze tijd!

Update uw browser om optimaal van deze website (en vele anderen) te genieten Nu updaten!

×